The WES Advisory Committee is scheduled to weigh a motion of support for a $266 million capital improvement plan at its Nov. 19 meeting.

The five-year Capital Improvement Plan (CIP) from Clackamas Water Environment Services covers fiscal years 2027/28 through 2031/32. It includes $239 million in wastewater projects and $27.4 million in surface water work, according to the meeting agenda. If the committee approves the motion, WES plans to present the CIP to the WES Board for adoption.

At an Oct. 22 WES Technical Advisory Team meeting, Jeff Stallard, WES capital program manager, presented the plan's major projects. The largest is the Tri City Wet Weather Program at $70 million, which would increase peak treatment capacity from 70 to 105 million gallons per day. Design and construction are slated for 2026 through 2031.

Other major projects Stallard presented to the Technical Advisory Team include the Middle Clackamas Interceptor at $33.3 million, the Tri City Influent Pump Station at $20.8 million and the Rock Creek Interceptor at $11.7 million. The pump station project calls for a complete electrical overhaul and replacement of all pumps.

Stallard told the Technical Advisory Team that costs are getting more expensive. He cited contractor availability and the regulatory environment as factors affecting both cost and schedule. Tariffs, he said, are also driving up costs. He told the team WES is asking the board for a 5% rate increase.

The CIP also prioritizes reducing inflow and infiltration (I&I) in aging sewer lines. A collection system master plan identified 19 basins that would have excessive I&I by 2040. That plan found $120 million in potential savings if a 65% reduction in I&I is achieved, because lining pipes costs less than building bigger treatment plants.

WES has already rehabbed 20,200 linear feet of mainlines, 648 linear feet of laterals and 98 manholes as part of that effort, according to the October Technical Advisory Team presentation.

The Nov. 19 meeting begins at 6 p.m. and is available by webinar. Greg DiLoreto, the committee chair, will call the meeting to order. Greg Geist, WES director, is scheduled to provide updates. The agenda also lists a presentation on advisory committee survey results by Alexa Morris, utility relations coordinator.

Residents can speak during a public comment period, with three minutes per speaker. Free language assistance is available by contacting WES at 503-742-4567 with 48 hours' notice.